Project Profiles

Sunville Rail is experienced in all aspects of civil engineering for the rail industry, including major signalling, construction and maintenance projects. We have a proven record in meeting high quality projects exceeding the expectations of our clients

Fratton Sidings

Completed:
December 19 - Ongoing

South Western Trains are increasing their sidings capacity at Fratton site installing 3 new sidings

View Case Study

Wessex Safer Isolations (NSCD's) Phase 3 GRIP 5-8

Completed:
October 19 - Ongoing

Sunville Rall contracted by Kiers to work on the Faster Safer Isolation technology project

View Case Study

Morden Train Depot Fencing

Completed:
September 2019

To remove existing palisade fencing and install new security Exmesh fencing at Morden train Depot

View Case Study

Kent CP5 750V DC Switchgear Renewals - Petts Wood

Completed:
November 2018

DC switchgear renewal at Petts Wood, and contruction of new TP hut

View Case Study

Victoria Area Re-Signalling Phase 2b

Completed:
November 2018

Victoria Area Re-Signalling Phase 2b Sutton & Wimbledon

View Case Study

Pangdean Substation Relocation

Completed:
June 2018

Pangdean – Substation Relocation

View Case Study

Raynes Park and Selhurst Area – SCADA

Completed:
August 2016

Raynes Park and Selhurst Area – Supervisory Renewals, Southern Region

View Case Study

Three Bridges Thameslink Depot

Completed:
October 2015

Civils works as part of the complete build and commission of a train care depot at Three Bridges.

View Case Study

Canterbury Area – Supervisory Renewals

Completed:
August 2015

The design, supply, construction civils and fibre works at 80 sites across the Canterbury ECR 

View Case Study

134573 - HV Switchgear Renewals

Completed:
December 2014

134573 HV Switchgear Renewals – Package D

View Case Study

Design and Construct Undertrack Crossing's for the DNO Project in the Kent Area

Completed:
November 2014 - May 2015

Undertrack crossing design and construct for the DNO project - Kent area.

View Case Study

Southern DC Traction PSE Wessex & Sussex Substations

Completed:
Feb 2014

Southern DC Traction PSE Wessex & Sussex Substations

View Case Study

BBD020 Tranche 2

Completed:
Jan 2013 to Nov 2013

Installation of 325km of 48 fibre cable route refurbishment , new cable route, Joint bays and UTX’s

View Case Study

Hollingbourne New Build

Completed:
September 2013

Sunville Rail were contracted to build a new brick built substation at the Hollingbourne site.

View Case Study

BBD020 Tranche 1

Completed:
Jan 2013

Installation of 335km of 48 fibre cable route refurbishment , new cable route, Joint bays and UTX’s

View Case Study

106412 – HV Cable Route Refurbishment project

Completed:
June 2016

106412– HV Cable Route Refurbishment project throughout Wessex ECR area

View Case Study

Accreditations